Mumbai Metro Line 3 (Aqua Line): Stations, Fare, Route Map, Status, & Timeline

Mumbai Metro

One of the first fully underground metro corridors in the city is Mumbai Metro Line 3, which is also referred to as the Aqua Line. A total of 27 stations are located along the line, where 26 stations will be underground and 1 station at grade.  It is around 33.5 km in length and is designed to connect the southernmost point of Mumbai, which is Cuffe Parade, to the western suburb of Aarey Colony. To alleviate congestion on the city’s overcrowded road and rail infrastructure, the Mumbai Urban Transport Project includes this high-capacity metro system as an essential component.

MMRDA granted autonomy of the line to the Mumbai Metro Rail Corporation (MMRC) to speed up the construction process and maintenance of the metro line. The Metro Line 3 project is being implemented by the Mumbai Metro Rail Corporation Limited (MMRCL). 

The construction work on the corridor commenced on 21st October 2016; however, it faced many legal disputes, which caused significant delays in the work. The Authorities eventually began construction activities at full scale on 18th May 2017.

The initial deadline for completing the Metro Line 3 project for phase 1 was 2021. However, due to the metro car shed issue, the project has been impacted severely, resulting in a cost escalation of over 10,000 crore.

As per the initial plan, the Metro Line 3 project was divided into two phases. The first phase (Bandra–Seepz) was planned to be completed by December 2021, and the second phase (Bandra-Kurla Complex – Colaba) by June 2022. Based on the previous plan, the entire stretch was expected to be operational by 2022.

An extension of the line has also been proposed to extend the line by 2.5 km to Navy Nagar from Cuffe Parade. As per the initial plan, Cuffe Parade was planned to be the first station of the line; however, after the extension, the first station will be Navy Nagar. There are 27 stations planned earlier, which will be 28 stations on the line after the extension is approved. The extension on metro line 3 will cost an additional ₹2,301 crore.

The Metro Line 3 corridor has 27 stations – Cuffe Parade, Vidhan Bhavan, Churchgate, Hutatma Chowk, CSMT, Kalbadevi, Girgaon, Grant Road, Mumbai Central, Mahalaxmi, Science Museum, Acharya Atre Chowk, Worli, Siddhivinayak, Dadar Metro, Shitala Devi Mandir, Dharavi, Bandra Kurla Complex (BKC), Bandra Colony, Santacruz Metro, CSMI-Airport – T1, Sahar Road, CSMI-Airport – T2, Marol Naka, MIDC-Andheri, SEEPZ and Aarey Colony (at Grade Level)

Mumbai Metro Line 3 (Aqua line) Current Status:​

  • On October 5, 2024, Prime Minister Narendra Modi inaugurated the 12.7 km Phase 1 of Mumbai Metro’s Line-3 (Aqua Line), which runs from BKC to Aarey JVLR. On October 7, 2024,  commercial operations started.
  • CM Fadnavis inaugurated the second operational segment, Phase 2A, on 10 May 2025. This 9.77 km route connects the Bandra Kurla Complex (BKC) to Worli at Acharya Atre Chowk. 
  • Currently Metro Line 3 (Aqua Line) is operational from Aarey Colony to Acharya Atre Chowk (Worli) (Please check below stations details to know more)
  • Acharya Atre Chowk (Worli)-Cuffe Parade (Last Phase)
    Construction is already underway on the last stretch, and CM Fadnavis stated that it should be finished by July or August 2025.

Mumbai Metro Line 3 - Quick Info:

Project/Metro NameMumbai Metro Line 3
Route/StretchCuffe Parade to Aarey Colony
Official Line ColorAqua
Status:Partially Operational
Length: 33.5 km
Total Stations: 27 Stations
Depot:
Construction Started:October 2016
Project Expected Completion Date: August 2025
Total Cost: ₹37,000 Crore
Detailed Project Report (DPR): DPR Link
Operator: Delhi Metro Rail Corporation (DMRC)
Estimated Ridership:
Website:mmrcl.com

🧳 Recommended Essentials for Your Metro Commute

Make your daily ride on the metro smoother with these commuter must-haves:

Some of the links in this article are affiliate links, which means we may earn a small commission if you buy through them, at no extra cost to you.”

Mumbai Metro Line 3(Aqua Line) Colaba - Bandra - SEEPZ Stations

Below is the list of stations on Metro Line 3 (Colaba-Bandra-Seepz) metro corridor. There are a total of 27 stations on the line, where 26 stations will be underground and 1 station at grade.

#Station NameStatusTypeConnections
1Cuffe ParadeUnder ConstructionUnderground
2Vidhan BhavanUnder ConstructionUnderground
3ChurchgateUnder ConstructionUndergroundWestern Line
4Hutatma ChowkUnder ConstructionUnderground
5CSMT MetroUnder ConstructionUndergroundCentral Line,Harbour line, Indian Railways
6KalbadeviUnder ConstructionUnderground
7GirgaonUnder ConstructionUnderground
8Grant RoadUnder ConstructionUndergroundWestern Line
9Mumbai Central MetroUnder ConstructionUndergroundWestern Line, Indian Railways
10MahalaxmiUnder ConstructionUndergroundWestern Line, Monorail
11Science MuseumUnder ConstructionUnderground
12Acharya Atre ChowkOperationalUnderground
13WorliOperationalUnderground
14SiddhivinayakOperationalUnderground
16Dadar MetroOperationalUndergroundWestern Line, Central Line, Indian Railways
17Shitala devi MandirOperationalUnderground
18DharaviOperationalUnderground
19Bandra-Kurla ComplexOperationalUndergroundInterconnect Mumbai Metro Line 2B – Yellow Line
20Bandra ColonyOperationalUnderground
21Santacruz MetroOperationalUnderground
22CSMI Airport – T1OperationalUnderground
23Sahar RoadOperationalUndergroundInterconnect Mumbai Metro Line 7 – Red Line
24CSMI-Airport – T2OperationalUndergroundInterconnect Mumbai Metro Line 7 – Red Line
25Marol NakaOperationalUndergroundInterconnect Mumbai Metro Line 1 – Blue Line
26MIDC-AndheriOperationalUnderground
27SEEPZOperationalUndergroundInterconnect Mumbai Metro Line 6 – Pink Line
28Aarey ColonyOperationalAt Grade (Ground Level)